Project Scope

The project involved the complete refurbishment of the existing office building originally constructed in 2000. The new facilities offer 75,000sq ft of grade A office space focused on wellbeing, remodelled to the highest specification with large, flexible floorplates, unrivalled facilities and superior finishes.

Summary

Location: 3 Rivergate, Redcliffe, Bristol BS1 6ER

Client: Credit Suisse Asset Management Limited

Architectural Design: AWW Architects

Project Manager: CBRE

Main Contractor: Paramount/Lancer Scott

Statistics

Project Duration: The refurbishment project completed in December 2024

Building Size: The building is seven storeys with semi-basement car parking and rooftop plantrooms.

Phased Works: The refurbishment works were phased to accommodate some of the existing tenants who remained in the building during the project

Contract Sum: £12m

Image credits: Lancer Scott & photographer Stephen Lewis

Location
3 Rivergate, Redcliffe, Bristol BS1 6ER

Client
Credit Suisse Asset Management Limited

Architectural Design
AWW Architects

Project Manager
CBRE

Main Contractor
Paramount/Lancer Scott

Project Duration

Completed in December 2024

Building Size

Seven storeys with semi-basement car parking and rooftop plantrooms

Phased Works

Phased to accommodate some of the existing tenants who remained in the building during the project

Contract Sum

£12m